Snohomish County Washington
Snohomish County Washington Public Works Roads Central
Click to search 
Public Works Roads Central
View Printer Friendly Page
Public Works Roads Central
Public Works
PW Services
Roads Central
Current Projects

logo Shortcuts
tree iconRelated Links
tree iconRelated Media
tree iconRelated Maps
tree iconRelated Services

eSubscribe Services
Subscribe to this page

Home  >  Departments  >  Public Works  >  PW Services  >  Roads Central  >  Current Projects  >  Swamp Cr Br 546


Swamp Creek Bridge #546 on Carter Road - (#RC1488)

Replacement project

 
Click to view a larger map

 

Project Description


Bridge #546, on Carter Road, spans Swamp Creek just north of the Snohomish—King County line in the Bothell area. Built in 1966, the bridge is a two-lane, timber and concrete structure which has required increased maintenance in recent years. A weight restriction of 16 tons is currently in effect. Snohomish County plans to replace this bridge in 2013*.

The new bridge will be longer and wider than the existing bridge. A feature of the new bridge will be five-foot wide sidewalks on both sides, replacing the current sidewalk which is only on one side. Five-foot wide shoulders will also be added to accommodate bicyclists. The longer bridge will span the creek eliminating the center piers which currently collect debris and can damage the bridge. Invasive plants near the bridge will be removed and replaced with native plants.

Construction of the new bridge is planned for the summer of 2013. A temporary road closure and detour route may be needed during construction. Notice will be given prior to the road closure.

 

Environmental Review


An environmental review of this project has been completed, in compliance with the State Environmental Policy Act (SEPA). A public comment period is now open. Please review the documents below and submit comments regarding this project via email or by mail to: Mary Auld, 3000 Rockefeller M/S 607, Everett, WA 98201. Comments must be received by May 31, 2011.

  • Notice of Land Disturbing Activity and SEPA Threshold Determination of
    Non-Significance (pdf) - May 2011 
  • Environmental Checklist (pdf) - April 2011 
  • Determination of Non-Significance (pdf) - May 2011 
  • Project Site Plan - (pdf)
  • Vicinity Map (pdf)
  • Aerial (pdf)

 

Past Mailings

  • Postcard, May 2011 (Notice of Land Disturbing Activity and SEPA Threshold Determination of Non-Significance)
  • Newsletter, January 2009 (pdf)
  • Newsletter, November 2006 (pdf) 
  • Newsletter May 2006 (pdf)

 

You can register to receive e-mail notification when information on this page changes by following this link. e-subscribe


Contacts

  • Steve Miller, Project Manager,  (425) 388-3488, ext. 4225
  • Mary Auld, Senior Environmental Planner, (425) 388-3488, ext. 4510
  • Jenean Hill, Right-of-Way, (425) 388-6681 
  • Tina Hokanson, Communications, (425) 388-3789

    (TTY: 425-388-3700)

 


* Construction schedules are subject to change based on a number of factors that include the availability of funding, length of the permitting process, coordination with other agencies, and weather.

Snohomish County's Road Construction Updates are issued weekly and are available online.

 

 

Snohomish County, Online Government Information & Services

County Home | Contact Us | Phone Numbers | Privacy Statement | Site Information | Feedback | Directions